Beaufort daylight
Northern Dancer Energy Inc.

Rising Sun Corridor.

The Project

Pipeline, modular compression, Mackenzie liquids, and a gravity-based Beaufort terminal built for year-round ice operations.

Infrastructure Overview

  • 42-inch dry gas line, 1,430 km, inside a 1 km energy corridor.
  • Up to 14 modular compressor stations — design one, build fourteen.
  • ~16,000 BPD condensate dryer at Inuvik for Mackenzie Delta gas.
  • 1.2 Bcf/d from the Alberta grid at Zama; 400 MMcf/d from the Mackenzie Delta.
  • Field construction late fall through early spring in warm enclosures. Modular fabrication at Zama and Inuvik in warm seasons.
  • Update the original Mackenzie Valley Gas process south of Inuvik. New permitting north of Inuvik to the GBS.
  • Gas Supply: 1.2BCF/day supply from the Alberta grid at Zama, AB & 400MMCF/day from the McKenzie Delta.
Route

Beaufort Sea terminal — GBS

Ice-class carrier

Development Roadmap / Milestones

WindowWork
Q4 2026 – Q3 2028Pre-FEED, feasibility, consultation, environmental permitting
Q2 2027 – Q3 2031Construction and major equipment manufacturing
Q2 2032Commercial start-up and first production

Stranded Gas Integration (Future)

Modular pre-investment at stations so regional First Nations can plug remote northern gas into local power or transport.